Update:  17th June 2016

This week, our contractors have begun the work extending the roof section for the new 'Secure Entrance.'  The main body of this work will be completed over the summer holidays.  Yet while the contractors were installing the roof for the new staffroom they also installed the roof for this new addition to our school.

Picture 1
Picture 2
Picture 3

Update:  26th July 2016

As the first week of the Summer holidays draws to a close, our builders have begun to dig the foundations for our new secure entrance.

Picture 1
Picture 2
Picture 3

Update: 29th July 2016

The foundations are well underway for the new Secure Entrance.

Picture 1

Update:  2nd August 2016

Our contractors have now created the foundations for this new area and have laid the concrete base.

Picture 1

Update:  5th August 2016

This week, our contractors have begun to block up one of the external windows, which will make a new display area for the Key Stage 1 Resource Area and have provided electricity to the new 'Secure Entrance.' 

Picture 1
Picture 2
Picture 3

Update:  11th August 2016

This week, our contractors have installed the new automatic doors, as well as the internal oak doors and the window has also been blocked up now  and the wall has been plastered-creating our new 'Secure Entrance.'  The undercoat has been applied to the new shelving area, within the Key Stage 1 Resource Area, ready for the final coat of gloss.

Picture 1
Picture 2
Picture 3

Update:  15th August 2016

This week, our contractors are finishing the new Secure Entrance: doors and ceiling installed, decoration complete; creating a new welcoming space, for parents and visitors.

Picture 1
Picture 2
Picture 3
This week, our contractors have begun laying the new path, leading from the car park to the new school entrance; making the entrance accessible to all.
Picture 1
Picture 2
Picture 3

Update:  17th August 2016

Our contractors have now completed the installation of the path, leading from the car park to our new Secure Entrance. It looks lovely!