Over the Summer Holidays, our contractors, will refurbish the Year 4, 5 and 6 Cloakroom areas.
Update: 5th August 2016
This week, our contractors have begun to prepare the cloakrooms, in advance.
Update: 11th August 2016
This week, our contractors have removed the 'old-style' cloakroom areas from the Year 4, 5 and 6 cloakrooms, ready for the installation of the new 'shoe-box' style cloakroom-next week. They have also removed the benching from the Year 4 and 5 shared area; opening the space up, which will be used as an intervention area, from September.
Update: 17th August 2016
Our contractors have started to install the new 'shoe box' units in to the Year 4 cloakroom.