Update: 20th May 2016
On Tuesday 17th May, the weather changed and work stopped outside. Our contractors moved their attention to the 'old staffroom,' where they sealed the internal doors. The room is now being prepared for the refurbishment:
Update: 3rd June 2016
Our contractors have begun to erect the internal walls which will form the new cloakroom area and internal classroom cupboard.
Update: 13th June 2016
Our contractors have been busy, these past weeks and have now moved the internal wall, thus extending the classroom, as well as making the classroom windows larger.
Update: 17th June 2016
This week, our contractors completed the 1st fix electrics, in readiness for the 'Plasterers' next week.
Update: 29th July 2016
What a transformation! The internal decoration is all complete.
Update: 17th August 2016
This week, our contractors have started to install the cloakroom, for the newly refurbished classroom.